Operating Costs of Gold Processing Plant
The dividing point between the two plants lies at the fine ore bin; all equipment prior to this bin is considered in the Crushing Plant and all equipment subsequent to it in the mill. General Design Criteria: Milling Rate = 500 tonnes/day (550 sptd) Crushing Rate = .